Further Tests
Engineer notice within 28 days
Right of Access
Untill the Performance Certificate
Performance Certificate
issue within 28 days
after the latest of the expiry dates
as soon thereafter as, supplled Documents and completed tested Works
state the date
copy to Employer
return the Perfomance Security within 21 days
Clearance of Site
Contractor remove all items
Employer dispose
Completion of Outstanding Work and Remedying Defects
Contractor
Cost of Remedying Defects
attributable to
Contractor
any design
Plant/Materials/workmanship
other obligation
Extension of Defects Notification Period
reason of a defect or damage, extended more than 2 years
Failure to Remedy Defects
notice
Contractor remedy
Employer
carry out himself/others, Contractor's cost
return Plant and Materials
recover all sums