施工概念
<span lang="ZH-TW"><b>施工特点</b>:(流里流气的许三多受军队影响大,)</span>
<p><span lang="ZH-TW"><b>施工项目:</b>路基土石方、涵洞、挡土墙、路肩、边坡、排水管线</span><span lang="EN-US"><o:p></o:p></span></p>
<p><span lang="ZH-TW"><b>施工流程:</b>交通导行一一技术安全交底(<b>项目技术负责人</b>依据施工方案向作业人员就工程难点、技术要点、安全措施交底)一测量放线</span><span lang="EN-US"><o:p></o:p></span></p>
<p><span lang="ZH-TW"><b>附属构筑物:</b>先地下后地上,先深后浅;管线拆改加固保护,修筑排水设施</span><span lang="EN-US"><o:p></o:p></span></p>
<p><span lang="ZH-TW"><b>路基土石方施工:</b>开挖路堑/填筑路基一整平路基一压实路基一修整路床一修剪防护工程</span><span lang="EN-US"><o:p></o:p></span></p>
施工技术
<span lang="ZH-TW">排除积水、清理树根杂草淤泥、处理坟坑井穴、分层填筑压实,湿土翻拌晾晒,干土加水,达到最佳含水量</span>
三种路基施工
<span lang="ZH-TW">挖土路基一一分层、严禁掏洞、管道边</span><span lang="EN-US">1</span><span><span lang="EN-US">m</span></span><span lang="ZH-TW">及缆线</span><span lang="EN-US">2</span><span><span lang="EN-US">m</span></span><span lang="ZH-TW">范围人工开挖、留压实量,雨水支管及检查井周围用石灰土或二灰砂砾填实</span>
<span lang="ZH-TW">填土路基一先找平、坡度陡于1:5修成台阶(高</span><span lang="EN-US">30</span><span><span lang="EN-US">cm</span></span><span lang="ZH-TW">宽</span><span lang="EN-US">1</span><span><span lang="EN-US">m</span></span><span lang="EN-US">),</span><span lang="ZH-TW">分层填筑,下层合格上层填筑,填筑宽度比设计每侧宽</span><span lang="EN-US">50</span><span><span lang="EN-US">cm </span></span>
<span lang="ZH-TW">石方路基一先码砌边部后填筑中部,管线及构筑物四周土料回填基设整平层,采用未筛分碎石和石屑或低剂量水泥稳定粒料(厚 10</span><span lang="ZH-TW">〜</span><span lang="EN-US">15</span><span lang="EN-US">cm</span><span lang="EN-US">)</span>
<p><span lang="ZH-TW">路基管道:管顶以上</span><span lang="EN-US">50</span><span><span lang="EN-US">cm</span></span><span lang="ZH-TW">不得使用压路机,覆土厚度不大于</span><span lang="EN-US">50</span><span><span lang="EN-US">cm</span></span><span lang="ZH-TW">时加固,50</span><span lang="ZH-TW">〜</span><span lang="EN-US">80</span><span><span lang="EN-US">cm</span></span><span lang="ZH-TW">时压实时保护和加固</span><span lang="EN-US"><o:p></o:p></span></p>
<span lang="ZH-TW">路基压实:方式一重力压实(静压</span><span lang="EN-US">)</span><span lang="ZH-TW">和振动压实,原则一轻静低慢叠4,轮外缘与路基边保持安全距离小型夯击防止漏夯,夯击面积重叠 </span><span><span lang="ZH-TW">1/4</span></span><span><span lang="ZH-TW">〜</span></span><span><span lang="ZH-TW">1/3 </span></span>
特殊季节施工
<p><span lang="ZH-TW">雨期施工:避开、分段集中施工、罩棚、留横坡、截水沟、当天挖完、填完、压完、不留后患 </span></p>
<span lang="ZH-TW">冬季施工:避开、覆盖、挡风、加热、保温,挖到设计标高立即碾压(下班后刨送覆盖),高等路不得含有土块,次高级路面冻土快不得大于<br></span><span lang="EN-US">10</span><span lang="EN-US">cm</span><span lang="ZH-TW">且含量小于15%</span>