E-business management platform (Phase 1)
System implementation (30 days Sprint)
Business Requirement
Identify business requirements
System construction
Project team setup
Project schedule
Identify work tasks according to the requirements
Daily Scrum meeting: share status and identify potential issues
Integration Test/UAT
functional test, verify data accuracy
Include auth concept test
Training
Internal Technology training
develop and publish own report
Data level: MDD, BI modeling, ETL
End User training
Go-live
Open questions
need to define the phases for whole project?
enough time on the database setup and modeling design?
define key review points ?
Data dictionary
Data warehouse design
MDD design
Authorization concept
for internal use: no DW concept?
Power BI server setup
for internal use purpose: can implement and publish own report/ analysis ?
configurable for authorization setup
Next Step